1 Design Principles

Fiber cement board and fiber reinforced silicate fireproof board factory design principles are: safe and reliable, advanced technology, economic and reasonable, protect the environment, promote structural optimization and upgrading and comprehensive utilization of resources, clean production, energy conservation and emission reduction.

The general plan of the factory

Small 1 technology and other facilities should be adopted

The design of calcium silicate board factory should be adapted to local conditions, and advanced, applicable, economical, reliable and energy-saving should be selected

There is equipment, the design scheme should be through the comprehensive comparison of multiple schemes; Expansion and reconstruction projects shall make full use of the original production

The quality of the flat should be reasonable from

And supporting facilities.

Development and production

Design procedure and design content

y fall, should be arranged in the injection workshop layout should pay attention to work

2.1 Design procedure

Transportation of raw materials, water and electricity

(1) Design preparation

Suoyi City is placed close to the workers

In the early stage of design, the chief design engineer shall, according to the requirements of the design contract and the provisions of basic information, organize various professionals to conduct on-site investigation and research, collect basic information, and verify the information and conditions provided by customers, that is, data collection.

(2) Prepare the commencement report

Should be close to the heat load center

The chief design engineer shall prepare the commencement report according to the contract and the provisions of commencement report preparation, which shall be approved by the chief engineer of the company

Management and living service facilities

Come into force. The contents of the commencement report include: project overview, design basis, project name and project code, construction scale and product plan,

The main people out of the population

Design scope and content, design principles, design technical requirements of each specialty, schedule arrangement, list of principals of each specialty, etc.

(3) Hold project commencement meeting and contract interpretation meeting.

The windward side of 1.

(4) Hold project finalization meetings and professional finalization meetings.

Greening and beautifying the environment of the area

(5) Each major shall carry out design, and provide data charts and data sheets to relevant majors. Generally, it is the craft major to provide the data chart and data sheet to other majors first, and then the majors carry out the design and provide the data chart and data sheet to each other.

Process layout drawing

(6) Each major shall form its own design finished product documents.

Product quality and yield

(7) All professional mutual materials and finished product documents shall be signed by design, proofreading and review level 3. Important materials and documents shall be signed by design, proofreading, preliminary review and review level 4, general drawing and other documents shall also be countersigned by relevant technology and other professionals.

2.2 Design content

In plane and space cloth

Fiber cement board and fiber reinforced calcium silicate board project factory construction drawing design involves general technology, electrical and self

Prepare to concentrate cloth

Dynamic, water supply and drainage, HVAC and air conditioning (including steam power), building, structure, general plan transportation, etc.

Placed in the factory area

Among them, the process design includes process layout, equipment table, material table, flow chart, pipeline chart (including slurry pipeline

District when building a factory, room

Diagram, pulp system pipeline diagram, vacuum system pipeline diagram, ash transport pipeline diagram, dust collection pipeline diagram, compressed air pipeline diagram, etc.), equipment safety

Dust pipe drawing installation drawing, equipment order drawing, non-standard parts production drawing, construction drawing specification and drawing catalog, etc.

The following provisions:

The design content and depth of other majors shall meet the requirements of relevant national regulations.